Legislation Details

File #: 26-0343    Version: 1 Name: FY2027 State of Good Repair Projects
Type: Consent Item Status: Consent Agenda
File created: 10/27/2026 In control: City Council Legislative Session
On agenda: 11/12/2026 Final action:
Title: Resolution to Request the Virginia Department of Transportation to Program Seven State of Good Repair Projects into its Six-Year Improvement Plan; to Amend the City Council’s Approved FY2027 Capital Fund (Capital Projects Fund) Budget to Incorporate each of those Projects; to Appropriate $3,329,352 of Available VDOT State of Good Repair Funds to the Capital Projects Fund for each of those Projects; and to Authorize the City Manager or Her Designee to Execute any Necessary Agreements
Attachments: 1. UPC_129613_129591_129593_129596_-_Hampton_.pdf, 2. UPC_129960_129961_129962_-_Hampton_City_-_A.pdf
Related files: 25-0306, 24-0475
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Resolution to Request the Virginia Department of Transportation to Program Seven State of Good Repair Projects into its Six-Year Improvement Plan; to Amend the City Council’s Approved FY2027 Capital Fund (Capital Projects Fund) Budget to Incorporate each of those Projects; to Appropriate $3,329,352 of Available VDOT State of Good Repair Funds to the Capital Projects Fund for each of those Projects; and to Authorize the City Manager or Her Designee to Execute any Necessary Agreements

 

Purpose

PURPOSE/BACKGROUND:

The Commonwealth Transportation Board approved, by Resolution on June 16, 2026, the State of Good Repair district funding distribution percentages for fiscal year 2027. Pursuant to Code of Virginia § 33.2-369, as amended, titled “State of Good Repair”, the Virginia Department of Transportation (“VDOT”) provides funding for reconstruction and replacement of structurally deficient state and locally owned bridges and rehabilitation of pavement, including municipality maintained primary extensions. The City of Hampton (“City”) applied and was approved for that State of Good Repair funding, and a total of $1,414,046 was allocated for four (4) projects, as follows: 609 Todds Lane Resurfacing Project ($127,978); 610 Todds Lane Resurfacing Project ($325,913); 611 Cunningham Drive Resurfacing Project ($429,747); 614 Todds Lane Resurfacing Project ($530,408).

 

In addition, in April of 2026, VDOT identified an available balance in the Hampton Roads State of Good Repair Local Paving program and offered localities an opportunity to apply for additional funding.  The City applied and was approved for additional State of Good Repair funding in a total amount of $1,915,306 to be allocated for three (3) additional projects, as follows: 692 Pembroke Avenue Resurfacing Project ($327,520); 762 Mercury Boulevard Resurfacing Project ($874,963); and 715 25th Street (Kecoughtan Road) Resurfacing Project ($712,823). 

 

All of these projects will enhance transportation within the City of Hampton. Once the allocations are accepted by the City, the funds are available immediately. VDOT has already assigned project numbers in anticipation of the City's approval of this request.

 

Discussion:

See Purpose/Background.

 

Impact:

See Purpose/Background.

 

Recommendation:

Rec

Approve Resolution

 

Body

                     WHEREAS, in accordance with the Virginia Department of Transportation (“VDOT”) project funding allocation procedures, the City Council, by resolution, must request VDOT program highway projects in the City of Hampton (“City”);

 

                     WHEREAS, VDOT indicated it is prepared to immediately allocate $3,329,352 of State of Good Repair funds to be used by the City for seven (7) resurfacing projects and has assigned UPC numbers to those projects in anticipation of the City’s request;

 

                     WHEREAS, those projects and associated amounts include: (1) 609 Todds Lane Resurfacing Project, UPC 129613 ($127,978); (2) 610 Todds Lane Resurfacing Project, UPC 129591 ($325,913);  (3) 611 Cunningham Drive Resurfacing Project, UPC 129593 ($429,747); (4) 614 Todds Lane Resurfacing Project, UPC 129596 ($530,408); (5) 692 Pembroke Avenue Resurfacing Project, UPC 129960 ($327,520); (6) 762 Mercury Boulevard Resurfacing Project, UPC 129961 ($874,963); and (7) 715 25th Street (Kecoughtan Road) Resurfacing Project, UPC 129962 ($712,823) (collectively referred to as the "Projects");

 

                     WHEREAS, federal and state funds have previously been allocated for this effort at 100% of cost and are available for disbursement to the City;

 

                     WHEREAS, project administration agreements with VDOT are necessary for securing VDOT commitment on those funds for the Projects; and

 

                     WHEREAS, the Projects were not previously included in the Capital Fund (Capital Projects) Fund of the City Council approved budget for fiscal year 2027 ("FY2027 Capital Budget").

 

                     NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF HAMPTON, VIRGINIA for the purposes of the Projects that:

 

                     1.  The Virginia Department of Transportation is requested to program the following seven (7) projects into its Six-Year Improvement plan, and allocate $3,329,352 of State of Good Repair funds as follows: 

 

                                          a)  609 Todds Lane Resurfacing Project, UPC 129613 ($127,978)

                                          b)  610 Todds Lane Resurfacing Project, UPC 129591 ($325,913)

                                          c)  611 Cunningham Drive Resurfacing Project, UPC 129593 ($429,747)

                                          d)  614 Todds Lane Resurfacing Project, UPC 129596 ($530,408)

                                          e)  692 Pembroke Avenue Resurfacing Project, UPC 129960 ($327,520)

                                          f)   762 Mercury Boulevard Resurfacing Project, UPC 129961 ($874,963)

                                          g)  715 25th Street (Kecoughtan Road) Resurfacing Project, UPC 129962 ($712,823);

 

                       2. The FY2027 Capital Budget is hereby amended to include those Projects;

 

                   3. The total sum of $3,329,352 to be received from VDOT shall be appropriated to the Capital Projects Fund for those Projects as itemized in Paragraph 1; and

                            

                    4. The City Manager or her authorized designee is hereby authorized to execute and deliver any and all documents necessary to carry out the purposes of this Resolution, subject to approval by the City Attorney.