File #: 22-0172    Version: 1 Name: River Street Park Appropriation
Type: Resolution Status: Passed
File created: 5/12/2022 In control: City Council Legislative Session
On agenda: 5/25/2022 Final action: 5/25/2022
Title: Resolution to amend the Fiscal Year 2022 Council Approved Budget and Accept and Appropriate to the Capital Budget (Capital Projects) Fund for the River Street Park Project, $113,490 Received from the Virginia Department of Transportation pursuant to the Memorandum of Agreement Regarding River Street Park
Indexes: Annual Budget Appropriations, DO NOT USE - 21 - Budget Adjustments, DO NOT USE - 21 - Placemaking
Title
Resolution to amend the Fiscal Year 2022 Council Approved Budget and Accept and Appropriate to the Capital Budget (Capital Projects) Fund for the River Street Park Project, $113,490 Received from the Virginia Department of Transportation pursuant to the Memorandum of Agreement Regarding River Street Park


Purpose
PURPOSE/BACKGROUND:
In order to address impacts to River Street Park (the “Park”) as a result of the Hampton Roads Express Lane Project Segment 4(c), the City negotiated a Memorandum of Agreement (the “Memorandum”) with the Virginia Department of Transportation (“VDOT”) regarding the Park. The Memorandum was fully executed by the City and VDOT on August 23, 2021. Under the Memorandum, there are two cost estimates that the City must submit to VDOT. The first cost estimate is related to the removal and relocation or storage of Park elements during the Project’s construction and the second cost estimate is related to the redesign of the Park following construction.

Following the City’s submission of the first cost estimate to VDOT and further discussions, VDOT signed a letter agreement on March 11, 2022, stating that VDOT would pay the City one hundred thirteen thousand four hundred ninety dollars ($113,490) for the removal and relocation or storage of certain Park elements during the Project’s construction. VDOT submitted the payment to the City via wire transfer on March 21, 2022. The source of the VDOT payment is the Hampton Roads Transportation Fund. The purpose of this resolution is to accept and appropriate the payment received by VDOT.

Discussion:

See Purpose/Background

Impact:

The VDOT payment will fund the City’s cost to remove and relocate or store certain elements of River Street Park during construction of the Hampton Roads Express Lane Segment 4(c) Project.

Recommendation:
Rec
Approve Resolution

Body
WHEREAS, the City of Hampton, Virginia (the “City”) and the Virginia Departm...