Skip to main content
 
File #: 26-0005    Version: 1 Name: Curve Delineation Project
Type: Resolution-Budget Status: Passed
File created: 12/23/2025 In control: City Council Legislative Session
On agenda: 1/14/2026 Final action: 1/14/2026
Title: Resolution to Request the Virginia Department of Transportation to Program the Curve Delineation Project into its Six-Year Improvement Plan; to Amend the City Council’s Approved FY2026 Capital Fund (Capital Projects Fund) Budget; to Appropriate $326,412 of Virginia Highway Safety Improvement Program Funds to the Capital Fund; and to Authorize the City Manager or her designee to Execute any Necessary Agreements
Attachments: 1. 127830 - Agreement Package
Title

Resolution to Request the Virginia Department of Transportation to Program the Curve Delineation Project into its Six-Year Improvement Plan; to Amend the City Council’s Approved FY2026 Capital Fund (Capital Projects Fund) Budget; to Appropriate $326,412 of Virginia Highway Safety Improvement Program Funds to the Capital Fund; and to Authorize the City Manager or her designee to Execute any Necessary Agreements

Purpose

The City of Hampton (the “City”) applied and was approved for Virginia Department of Transportation (“VDOT”) Virginia Highway Safety Improvement Program funds for the Curve Delineation Project (the “Project”).

In accordance with the VDOT project allocation procedures, in order to receive VDOT funding support, City Council must request by resolution that VDOT program each highway project; and must authorize the City Manager or her designee to execute project administration agreements and any other City/State Agreements for implementation of the Project.  Once approved and programmed, VDOT will allocate sufficient federal and state funds to fully fund the Project.  The funds are to be paid on a reimbursement basis from VDOT to the City following the expenditure of City funds.

Rec

Approve resolution

Body

                     WHEREAS, the City of Hampton (the “City”) applied and was approved for Virginia Department of Transportation (“VDOT”) Virginia Highway Safety Improvement Program funds for the Curve Delineation Project (the “Project”);

                     WHEREAS, in accordance with the VDOT project funding allocation procedures, the City Council, by resolution, must request VDOT to program highway projects in the City;

                     WHEREAS, project administration agreements with VDOT are necessary for securing VDOT commitment on those funds for the Project;

                     WHEREAS, VDOT will allocate sufficient federal and state funds to fully fund the Project;

                     WHEREAS, VDOT ...