File #: 19-0332    Version: 1 Name: Salt Ponds Inlet
Type: Resolution-Budget Status: Passed
File created: 10/31/2019 In control: City Council Legislative Session
On agenda: 11/13/2019 Final action: 11/13/2019
Title: Resolution Authorizing an Increase of More than 25% of Original Contract Price Awarded Under ITB 19-47/CLP to Coastal Design & Construction, Inc. for Salt Ponds Beach Inlet Improvements - Phase 2 as Required by Hampton City Code § 2-336
Indexes: , Stormwater
Title
Resolution Authorizing an Increase of More than 25% of Original Contract Price Awarded Under ITB 19-47/CLP to Coastal Design & Construction, Inc. for Salt Ponds Beach Inlet Improvements - Phase 2 as Required by Hampton City Code § 2-336

Purpose
PURPOSE/BACKGROUND:
In 2019, the Department of Public Works solicited a formal bid under ITB 19-47/CLP for the construction and completion of a rock jetty on the south side of the inlet, a rock spur off of the north jetty and sand tightening along the north rock jetty at Salt Ponds Inlet. The bid was awarded to Coastal Design & Construction, Inc. as the lowest responsive and responsible bidder at a quoted price of $2,381,286.00. Subsequent to the award, a change order was submitted and approved for the sand tightening of the new south jetty in the amount of $39,000. The dredging of the channel is necessary to remove the accumulation of silt and will benefit the overall improvements to the inlet. This will require an additional change order expected to be in the sum of approximately $715,000. However, because the contractor is currently onsite, this amount does not include additional costs for mobilization/demobilization which is a savings of approximately $100,000. The funding for the initial project and proposed dredging is available from General Obligations Bonds issued in FY15 and FY18 for Salt Ponds projects. The cumulative total of change orders is $754,000, which equates to an approximate 32% increase over the original contract price. Hampton City Code § 2-336 requires the advanced written approval of City Council in order to increase a contracted amount by more than 25% or $30,000, whichever is greater.

Discussion:

Approval by City Council to increase the contract price would allow the department to issue a change order modifying the contract to dredge the channel during construction. The scope of work under the existing contract with Coastal Design & Construction, Inc. consists of the construction an...

Click here for full text